CHECKLIST BEFORE START OF UNIT FIT-OUT/RENOVATION WORKS (Please Read)
Please submit to Adriatico Grand Residences - Management Office the items listed below by Finishing/Fit-out and Renovation Contractor:
A. FIT-OUT WORKS:
Name of the sub-contractor, and list of workers (maximum of 6 pax), bar chart and fit-out plan.
Photocopy of the receipt for a newly refilled fire extinguisher, minimum of 10lbs. ABC type. (To signify it is a new and working apparatus).
Fire extinguisher unit must be brought inside the unit, prior to the renovation works and during the whole renovation period.
Renovation cash bond - Php ____________ (Refundable).
Review and Inspection/Coordination Fee - Php 3,000.00 (Non-refundable).
Notice to Proceed (NTP) to be applied by Unit Owner allowing the contractor to start the work, but it is not valid without the issuance of work permit by the admin.
Prescribed uniform for the workers.
B. RENOVATION WORKS:
All fit-out works checklist items. (A-1 to A-7).
1 - Set of primary renovation plans for review and approval by Building Committee Office if the plan changes from the existing structural, plumbing, or electrical work.
2 - Sets of the following items:
Complete renovation plan (20 X 30) with signature and seal by a Civil Engineer, Architect or Interior Designer.
Specification (legal size bond paper) with signature and seal by Civil Engineer, Architect or Interior Designer.
Detailed list of scope of work.
Checked and approved plans & specifications will be done by Building Committee.
Re-tiling of toilet and bath; re-tiling of balcony tiles are not allowed.